On March 4, 2008, the
Wisconsin Supreme Court will hear oral
arguments in a case with important
implications regarding the exposure of
Wisconsin contractors to claims and criminal
prosecution for theft by contractor.
State v. Keyes, 2007 WI App 163, 736,
N.W.2d 904; petition for review granted
2007 WI 134, 742 N.W.2d 524.
Most contractors are
familiar with the general rules regarding
their rights and responsibilities under
Wisconsin’s theft by contractor statutes.
Under section 779.02(5) of the Wisconsin
Statutes, any money paid to a prime
contractor or subcontractor for the
construction of improvements on land is a
“trust fund” for amounts owed by the prime
contractor or subcontractor for labor,
materials, and services performed or
provided on the project. Use of the money
for purposes other than project expenses
before all claims related to the project
have been paid is considered theft by
contractor and may be punishable as criminal
theft under Wis. Stat. § 943.20.
In the 2007 Keyes
case, the Court of Appeals held that a
prime contractor acting as a subcontractor
can pay itself for labor and materials
before other subcontractors, but not for
profit on those materials. Angela and
Matthew Keyes owned the La Crosse
construction company Keyes to Design Inc.,
which acted as general contractor on a house
building project. Angela Keyes also
performed services on the project as a
subcontractor. The Keyes were charged
individually with felony theft by contractor
under Wis. Stat. §§ 779.02(5), 939.05, and
943.20(1)(b) and (3)(c) because they kept as
a profit approximately $36,000 from the
project and did not make payment in full to
all subcontractors and suppliers. The Keyes
contended that as a subcontractor on the
project, Angela was entitled to receive
payment for materials provided plus profit
even though other subcontractors had not
been paid in full.
The decision appears to
reiterate two basic rules for general
contractors to follow. First, the general
contractor has the same claim to funds as a
subcontractor with respect to reimbursement
for its labor and materials. Second, the
general contractor is at risk with respect
to profit and indirect costs (e.g. overhead)
until all subcontractors and suppliers are
paid in full.
Under a narrow
interpretation, the Keyes decision
may be limited to its facts, i.e. apply only
to general contractors who self-perform work
or perform through a related entity.
However, the decision can potentially be
read more broadly to prohibit general
contractors (and subcontractors with their
own subs and suppliers) from paying overhead
and profit to unrelated
subcontractors until all labor and materials
on the project are paid. Certainly, such a
broad application does not mesh well with
the realities of a typical construction
project or the expectations of contractors.
Hopefully, the
Wisconsin Supreme Court will adopt a narrow,
common sense reading of the lower court’s
decision, recognizing the realities of the
construction industry and the concern that
many small and mid-size contractors do not
have the resources to survive without a
profit until the completion of a project.